Progress summary
Construction activities are progressing well and are on program. Key construction activities completed/ongoing during May 2017 are:
- Piling
- Ground floor slab
- Detailed excavation
- Formwork
- Reinforcement
- Completion of retaining wall
A community information booth was held on 27 April 2017 at Cherrybrook Technology High School.
Next steps and key events
- Ground floor slab
- Ground floor walls
Upcoming information booths
School and community information booths will be scheduled for June/July 2017. Exact date and time to be advised.
For any additional information, please contact Long Nguyen at Coffey – appointed Project Managers of the Capital Works project.