Progress summary
Construction activities are progressing well and are on program. Key construction activities completed/ongoing during July 2017 are:
- Ground floor slab near completion
- OSD tank near completion
- Commencement of block work to upper levels
Next steps and key events
- Ground floor slab section 3
- Formwork
- Reinforcement
- Concrete pour
- Ground floor walls construction
- Level 1 preparation works to sections 2 and 3 including
- Formwork props
- Formwork
- Reinforcement
- Concrete pour
Upcoming information booths
School and community information booths will be scheduled for August 2017. Exact date and time to be advised.
For any additional information, please contact Marty Smith at Coffey Projects – appointed project managers of the capital works project.